gensokyo-devandgensokyo-dev 07e4b700ac test: let the deadline policy own test waits
Vitest's expect.poll and vi.waitFor stop after one second by default, a
host-speed guess that the project's deadline policy does not see. Under
hosted-CI load, kunaProjectConcurrency failed that way twice on unrelated
PRs. Another 256 waits relied on the default, and 97 passed literals
picked to fit some host.

Waits now take as long as their test may run, less the reporting reserve
that children already keep. Each Vitest project sets expect.poll's
default, and the new waitFor in tests/support/testWait.ts replaces
vi.waitFor. Fixture readiness waits (awaitAcknowledgement and the provider
process waits) default to the same deadline, and their host-speed literal
arguments are removed. One remainingTestDeadline owns the arithmetic for
both children and waits.

Ten waits whose short timeout was the real check now assert it directly
(Kuna version probe, Cutter discovery, doctor and Inspector cancellation,
apktool fixture teardown, JADX disconnect): settlement before the
production deadline that would otherwise also satisfy the wait, or a
deadline pinned beyond every test deadline.

The rea/project-wait-deadline lint rule rejects vi.waitFor and explicit
expect.poll timeouts. The testing guide and the CI tests audit skill now
document the policy.

Co-Authored-By: gensokyo-dev <342580529+gensokyo-dev@users.noreply.github.com>
2026-11-14 19:28:38 +08:00
ee1450b5d4 test: bound every test process registry by the running test
Registries created directly with createTestProcessRegistry did not get the
processTest default, so a hung child there had no deadline once its explicit
value was removed; Vitest's test timeout does not settle the awaited run, so
shutdown was never reached. Derive the default in the registry from the
running test instead, using the real clock.

Co-Authored-By: gensokyo-dev <342580529+gensokyo-dev@users.noreply.github.com>
Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-11-14 13:21:13 +08:00
077bebe49b test: bound fixture child processes by the remaining test deadline
A processTest child run without its own timeoutMs now gets the test's
remaining deadline less a reporting reserve (at least 5 seconds, or a
tenth of the deadline). A hung child still fails with its captured output,
without a fixed per-call value that assumes a host's speed.

Co-Authored-By: gensokyo-dev <342580529+gensokyo-dev@users.noreply.github.com>
Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-11-14 13:21:13 +08:00
46728ca41d test: remove per-test deadlines owned by project policy
Explicit deadlines at or below the project deadline only shortened it:
a literal 30-second value also disabled the coverage scaling, which timed
out wide-capacity regressions on main. Workloads above the built
deadline use the long-running tag. Deadlines derived from an operation
budget remain.

Co-Authored-By: gensokyo-dev <342580529+gensokyo-dev@users.noreply.github.com>
Co-Authored-By: Claude Opus 5.5 <noreply@anthropic.com>
2026-11-14 05:27:07 +08:00
morluto 38dc9d246b test: own and bound Electron hook fixture processes 2026-11-10 16:32:53 -05:00
morluto 60149282fc test: strengthen integration oracles and verification (#8295)
* test: strengthen integration oracles and verification

* test: bound lifecycle gates and strengthen workflow checks

* test: verify complete paged and extracted results

* test: preserve bytecode and cancellation evidence

* test: strengthen retained evidence and fixture cleanup

* test: require cross-projection bridge identities

* test: retain fixture owners through cleanup failures

* test: verify graph examples and project selectors

* test: tighten provider and lifecycle regressions

* test: consolidate hex coverage and bound cutter cleanup

* test: bound subprocess output waits and strengthen graph checks

* test: check mcp recovery and preserve cleanup owners

* test: verify structured mcp argument failures

* test: preserve artifact cleanup and gdb limit evidence

* test: preserve evidence identities and bound provider gates

* test: retain browser and comparison cleanup owners

* test: bound startup and strengthen fixture oracles

* test: bound lifecycle gates and verify recovered evidence

* test: verify public outcomes and lifecycle ownership

* test: assert precise evidence and release lifecycle gates

* test: verify selected facts and bound cleanup waits

* test: check retained evidence and decoded records

* test: verify final reports and retain cleanup ownership

* test: bound reviewed startup gates and retain cleanup

* test: verify PE errors and preserve MCP cleanup

* test: preserve MCP fixture cleanup ownership

* test: release provider gates before late startup